How to stop the vertical roller mill

Read Time:37 Second



Starting sequence of Vertical roller mill is: first to lubricating oil pump of vertical roller mill, when the oil pressure reaches 1.5-2.0 kg/cm, it is allowed to start the vertical roller mill, and then start the classifier. When everything is OK, we bagin to feeding.

At last, when stop the vertical roller mill, first to stop the feeding machine. After the ore treatment is finished, stop the vertical roller mill motor, and finally stop the pump. Use the lifting device of the classifier to lift the spiral out of the sand surface, and then stop the classifier.

This is daily Operation and Maintenance of Ball Mill, if you have other queation about vertical roller mill, please connect with us.



0 0
Happy
Happy
0 %
Sad
Sad
0 %
Excited
Excited
0 %
Sleppy
Sleppy
0 %
Angry
Angry
0 %
Surprise
Surprise
0 %

Leave a Reply